04.03.2026 - Press Release - Hillsboro Road and Meramec Station Road Stormwater Improvements Project

city

Hillsboro Road and Meramec Station Road Stormwater Improvements Project
Project Status Update
April 3, 2026

Primarily due to the weather conditions, some of the projected dates of completion for this project have been pushed back. As the project nears completion, certain tasks must be completed before other tasks can be completed. When the weather pauses activity on the project, exponential additional delays are experienced because of it.
\
The table below lists several tasks and the updated projected date of completion for each of the tasks.
The contractor provided an updated schedule on April 2nd, and these dates were taken directly from that
updated schedule. As always, the projected dates of completion are weather dependent.

Task Name or Description                                                                                      Projected Date of Completion
Installation of remaining sections of guardrail                                                                        April 13, 2026
Installation of remaining concrete curb and gutter                                                               April 30, 2026
Installation of asphalt overlay drive surface on Hillsboro Rd.                                         May 8, 2026
Hillsboro Rd. open to traffic                                                                                                                  May 12, 2026
Project final completion date                                                                                                                May 26, 2026


Once Hillsboro Road is open to traffic, the remaining tasks, mostly located on Meramec Station Road, will be completed under flagging conditions. Please exercise care and caution as you travel through the worksite.
The following pages contain photos of some of the work that has been completed and some items that are in the process of being completed. All the photos on the following pages are traveling northbound on Hillsboro Road and were taken on the afternoon of Thursday, April 2nd.
We understand the inconvenience and frustration this project has caused, especially since the original construction timeline indicated this project would be finished four months ago. The City shares your frustration, and we are grateful for your continued patience. Please contact me with any questions, comments, or concerns.

Nathan Schauf, City Administrator